    Hi All,

    New T50 operator here. I am looking to set up a batch tank/IBC system on a shoestring (spent all my money on a drone!) budget. Needs to be able to fill T50 at a decent rate as well as agitate product. I have a large generator capable of running a 240v pump alongside the T50 charging station. Any ideas welcome!

    HCAA
    Participant
    Post count: 4

    G’Day Dodds,

    I don’t have a definitive answer but I would give some consideration to the amount of product you are batching at a time.

    I mostly run my T25 because of the mountains that I work in  95% of the time, however, I mix 600 litres per batch if possible.

    It’s difficult to hit the KPI’s if you have to stop continually to make a batch.  Easier if you have a sidekick but I don’t know anyone that can make a batch in the 90 seconds to 4 mins it takes to drop the previous load.

    Hope it works out well on your new venture.

    Ian